Below are
approximations that may vary from actual closing and completion.
Building E: Building is all closed. Punch line items are
being corrected.
Building F: Building is all closed.
Building G: CO will be taking place week of March 14th.
Closings will take place within the next 10 days.
Condo Flats: Installation of Hardie Board siding and
stucco lathe are being applied & Galvalume roof is almost
complete. Electrical has been wired and drywall has been roughed
out. Hard contracts have started.
|